Process & Timeline

how the build runs, what each release depends on, and how this sits alongside the main website

The build runs inside mowp.org's Q4 pause and opens for bookings ahead of the first events. Photography follows the first season. Whether a single interest page goes up ahead of all of it is still open; see Scope.

Decide and confirm

Sept 2026

The option, and the capacity and dimension numbers from the drawings

Build

Oct – Dec 2026

Inside the main site's Q4 pause, so the two don't compete

Private preview

Jan – Feb 2027

For internal partners

Public, accepting bookings

Feb – Mar 2027

Listings live, inquiries start collecting

First events

May – Jun 2027

The first real photography becomes possible

Photography pass

Later 2027

Renderings replaced with photographs, plus testimonials and a gallery

The sequence

Settle the option, naming and the domain

The choice of option and whether the space markets under MOWP's brand decide the domain, and the domain decides where every listing built afterwards points.

Gather what exists

Renderings from Scott Edwards Architecture, architectural floorplans, capital campaign material and whatever specifications the drawings already carry.

Confirm the known numbers

Capacity, dimensions and what comes with the room. These are lookups from the drawings rather than decisions, and they're what makes the pages worth publishing.

Build and review

Eight pages and one inquiry form, with two review rounds.

Launch and list

The pages going live are half of it. The Google Business Profile and the directory listings are the other half, and they take longer to take effect than the build does. See Directories & Listings.

What blocks what

DependencyWhat it blocks
RatesThe pages exist either way, but a rates page without rates is worse than no rates page
Operating policiesAlcohol, insurance, vendors, hours and noise. These come from whoever runs the space, and they can't be guessed
A finished roomThe photography pass. Renderings carry the launch; photographs replace them after the first events
One real eventThe first photographs of the room in use. Worth planning a shoot around the opening event
NoteA soft-launch event is an early way to get real photography.

Photograph an opening event MOWP is already holding.

Sequencing against the main website

mowp.org builds through September, pauses through Q4 for year-end giving, and launches in February 2027. The venue build sits inside the pause, so the two don't compete for the same weeks. On option 3 the venue pages launch with mowp.org; options 1 and 2 can launch on their own schedule.

Review rounds

Two, priced in the Estimate: one on structure and content before the pages are built out, one on the built site before launch.